Start
16 Jul
Target
23 Dec
Progress
8/15
Overdue
0
Concept
16 Jul – 6 Aug4/4Kick-off & briefCritical path
Concept & mood boardsCritical path
Client concept approvalClient approvalCritical path
◆Concept signed offVisible to clientCritical path
Design development
6 Aug – 3 Sept3/3Furniture schedule & drawingsCritical path
Client drawing approvalsClient approvalCritical path
Weekly client status update
Procurement & production
3 Sept – 2 Nov1/3Place supplier ordersCritical path
Production follow-upsCritical path
◆Production completeVisible to clientCritical path
QC & shipping
2 Nov – 7 Dec0/2QC all piecesCritical path
Consolidate & shipCritical path
Install & styling
7 Dec – 17 Dec0/3Install dayCritical path
Styling & handoverCritical path
◆Project handoverVisible to clientCritical path
To do
6◆Production complete
Procurement & production
👁 1⛓ 131 OctOOQC all pieces
QC & shipping
⛓ 17 NovLLConsolidate & ship
QC & shipping
⛓ 15 DecSInstall day
Install & styling
⛓ 19 DecOOStyling & handover
Install & styling
⛓ 112 DecA◆Project handover
Install & styling
👁 1⛓ 113 DecOO
In progress
1Production follow-ups
Procurement & production
⛓ 130 OctLL
Done
8Kick-off & brief
Concept
☑ 2/319 JulOOConcept & mood boards
Concept
💬 3📎 3⛓ 129 JulSClient concept approval
Concept
⛓ 13 AugS◆Concept signed off
Concept
👁 1⛓ 13 AugLLFurniture schedule & drawings
Design development
⛓ 120 AugLLClient drawing approvals
Design development
⛓ 130 AugLLWeekly client status update
Design development
↻ weekly7 AugOOPlace supplier orders
Procurement & production
⛓ 110 SeptA
October 2026
Fri
30
- Production follow-ups
Sat
31
- ◆ Production complete
- Production follow-ups
- Production complete
Comments
- A
Admin · 9h ago · Concept & mood boards
Looks good — please attach the final elevation.
- OO
Olive Ops · 1d ago · Concept & mood boards
Factory confirms 21 days. @sales client prefers the warmer ivory.
- S
Sales · 1d ago · Concept & mood boards
@ops can we confirm the fabric lead time before sign-off?
Activity
- Status update: on track Olive Ops · 5h ago
- Looks good — please attach the final elevation. Admin · 5h ago
- Factory confirms 21 days. @sales client prefers the warmer ivory. Olive Ops · 5h ago
- @ops can we confirm the fabric lead time before sign-off? Sales · 5h ago
- Production follow-ups → in_progress 5h ago
- Place supplier orders → done 5h ago
- Weekly client status update → done 5h ago
- Client drawing approvals → done 5h ago
- Furniture schedule & drawings → done 5h ago
- Concept signed off → done 5h ago
- Client concept approval → done 5h ago
- Concept & mood boards → done 5h ago
- Kick-off & brief → done 5h ago
- Applied template: Full home furnishing 5h ago
- Task created: Project handover 5h ago
- Task created: Styling & handover 5h ago
- Task created: Install day 5h ago
- Task created: Consolidate & ship 5h ago
- Task created: QC all pieces 5h ago
- Task created: Production complete 5h ago
- Task created: Production follow-ups 5h ago
- Task created: Place supplier orders 5h ago
- Task created: Weekly client status update 5h ago
- Task created: Client drawing approvals 5h ago
- Task created: Furniture schedule & drawings 5h ago
- Task created: Concept signed off 5h ago
- Task created: Client concept approval 5h ago
- Task created: Concept & mood boards 5h ago
- Task created: Kick-off & brief 5h ago
Week 17 Oct – 23 Oct
Drawings approved and production is under way.
- Highlights
- Fabric confirmed; frames assembled.
- Risks
- None this week.
- Next steps
- QC inspection booked for next week.
Client visibility is a staff toggle; the portal shows it on the client’s next visit. Nothing is emailed.
elevation-v2.svg
18 KB
swatch-board.svg
16 KB
- PDF
spec-sheet.pdf
240 KB
Budget vs actual
Admin & finance only · actuals from QuickBooks (mock)| Category | Budget | Actual | Used |
|---|---|---|---|
| Freight | SGD 4,200 | SGD 4,900 | 117% |
| Furniture | SGD 38,000 | SGD 34,300 | 90% |
| Installation | SGD 1,800 | SGD 0 | 0% |